Half the Data Centers in the Headlines May Never Get Built. So Is the One Near You Even Real?
Updated September 13, 2026
There's a data center coming to a field near me — at least that's what the announcement said. Then the town over got the same news. Then a few more. And I started to wonder if all of these were really happening, or if I was just reading the same hopeful press release on repeat. Turns out I was right to be suspicious: a huge share of the data centers making headlines will never turn into a single pour of concrete. Once you know what to look for, you can usually spot which ones are real.
A press release isn't a shovel
The first thing that broke my brain is that an announcement barely means anything. It's closer to getting in line than breaking ground. A developer files to reserve a grid connection, and that filing costs them almost nothing — no land, no signed customer, no financing needed just to raise their hand.
So the line fills up with everybody. Big names you'd expect, sure. But also land brokers, investment funds, and shell companies that don't own the dirt, don't have a tenant, and couldn't tell you what color the building's going to be. They grab a spot, bet that "powered land" will be worth something later, and wait.
Think of it like grabbing eight dinner reservations for the same Friday so you can pick later which one you actually want. Seven of those tables sit empty, but every restaurant already thinks it's booked solid. That's roughly what's happening to the power grid right now.
The number that made me stop trusting the map
Texas runs its own grid, and it keeps a public tally of everyone who's asked to plug in. Last time I checked, those requests added up to more than five times the most electricity the entire state has ever used at once — every home and factory and air conditioner in August, times five.
The amount actually built and running? Somewhere around one percent of it.
That's not just a Texas quirk. Grid analysts figure roughly two-thirds of the data center power being requested across the country will never materialize. One utility in Ohio got tired of guessing and simply asked developers to sign a real, long-term contract to pay for the power they were reserving. The moment there was actual money on the line, about two-thirds of the pipeline evaporated. The serious projects stayed. The reservations-of-convenience walked.
So how do you spot a real one?
Once I stopped trusting announcements, I started hunting for the boring paperwork underneath them, because the real ones leave a trail the fake ones don't.
A real project usually has a signed power deal, not just a spot in line. It's filed the engineering studies to prove the grid can actually feed it. There's a named tenant — an Amazon or a Microsoft or a Meta — with money committed, instead of a mystery LLC. And my favorite tell: somebody's ordered the actual engine. The big gas turbines that spin these generators are so backed up that if you placed an order today, you might not see it until around 2031. Nobody waits six years in line for a building they're not serious about.
The flip side is a project that's all press release and no plumbing, and those have started falling apart in a big way. Cancellations jumped several-fold in a single year, with something like a hundred billion dollars of projects blocked or stalled in one spring alone. Some of that is neighbors showing up to zoning meetings. A lot of it is the simple physics of power that was never really there.
The part nobody puts in the announcement
The canceled projects aren't even the interesting part. What got me is everything humming behind the ones that are real — the turbines on back-order, the substations, the water it takes to keep the servers cool, and the quiet question of whose electric bill covers all of it.
Once you start pulling that thread, it goes a lot further than one field near your house. That's the whole rabbit hole we chase on Byte Bungalow: the machines behind the grid and the people paying for them. If you want to see where this one leads, go watch the video and subscribe on YouTube. I'll keep doing the homework out loud.
Common questions
How can I tell if a data center announced near me will actually get built?
Why would a company announce a data center it never intends to build?
Will a data center near me raise my electric bill?
Do all these cancellations mean AI is a bubble?
Why does it matter that gas turbines are back-ordered?
Keep reading
My Electric Bill Doubled and I Can't Move. Here's the First Lever I Pulled.
Retired, bill doubled from the data center boom, stuck in your house? The cheapest real lever isn't using less power. It's a phone call. Here's what I found.
A packed room made the developer walk — so why did the people who won tell everyone not to cheer yet?
Does showing up to a town hall actually kill a data center, or just push the vote to a quieter night? I dug into what really happens after the room clears.
To Escape Data-Center Rate Hikes With Solar — Is Rooftop a Trap and Ground-Mount the Smarter Buy?
Data-center rate hikes push homeowners to solar. Is rooftop a trap and ground-mount smarter? What leaks, insurance, and resale do to the real math.
They Already Voted Yes on the Data Center — So Why Are There Still Two Decisions Left?
The data center vote already passed? It's not the last decision. Here's the air permit and utility rate case you can still weigh in on.
Why Don't Data Centers Cool With Treated Sewage Instead of Your Drinking Water?
A lot of data centers already cool with treated wastewater. The ones that don't usually can't — and the reason comes down to a purple pipe.
If the Ocean's Right There, Why Cool Data Centers With Drinking Water?
The ocean's right there — so why cool data centers with drinking water instead of seawater? A few already do. Here's why it's rarer than you'd think.
Sources
- datacenterwatch.org — **$98 billion** in potential investment blocked or delayed in **Q2 2025 alone** (late March–June 2025), more than all disruptions tracked since 2023 combined; **20 projects** block
- gizmodo.com — Cancellations **quadrupled in 2025** (6 in 2024 → 25 in 2025; 2 in 2023). "Several-fold in a single year" framing.
- yahoo.com — Confirms quadrupling amid community pushback; 21 of 25 canceled projects terminated in H2.
- globaldatacenterhub.com — **An announcement = "a request for electricity, not a commitment to build."** ERCOT April 2026: **445.8 GW requested through 2033, ~9 GW approved to energize, <3.9 GW actually oper
- utilitydive.com — Utilities see **5–10x more interconnection requests than actual builds**; **Wood Mackenzie: two-thirds of data center power requests won't materialize.** ERCOT tracking **474 GW**
Byte Bungalow
I do the homework out loud.